    May 2026

    Reinforcement steel works were inspected by structural consultants BASE. Concreting of column footings for Tower D was successfully completed.

    April 2026

    DMC piling activities progressed steadily, while excavation and PCC laying works were undertaken for Tower D foundations.

    April 2026

    Shifting of old wooden planks and battens has been completed.Tower D footing and shuttering work is currently in progress

    March 2026

    Construction of the diaphragm wall was completed. Project machinery underwent inspection and received green-tag certification for operational readiness.

    March 2026

    Construction activities have started at the site. The dream has started to take shape.

    February 2026

    Site preparation and construction staging activities commenced, establishing the groundwork, logistics, and infrastructure required for project execution.

    May 2026

    Reinforcement steel works were inspected by structural consultants BASE. Concreting of column footings for Tower D was successfully completed.

    April 2026

    DMC piling activities progressed steadily, while excavation and PCC laying works were undertaken for Tower D foundations.

    April 2026

    Shifting of old wooden planks and battens has been completed.Tower D footing and shuttering work is currently in progress

    March 2026

    Construction of the diaphragm wall was completed. Project machinery underwent inspection and received green-tag certification for operational readiness.

    March 2026

    Construction activities have started at the site. The dream has started to take shape.

    February 2026

    Site preparation and construction staging activities commenced, establishing the groundwork, logistics, and infrastructure required for project execution.