    Construction Update

    From Vision to Reality

    Building a landmark, one milestone at a time

    Aug 2026

    Construction is progressing steadily at Indumati Palace Residences, with slab shuttering and steel binding underway at Towers A, B & C, while column binding work is in progress at Tower D.

    Aug 2026

    Construction is progressing steadily at Indumati Palace Residences. Tower A’s raft concrete is complete, column casting is underway in Towers C & F, and Tower D’s first slab is ready for casting.

    July 2026

    On-site development continues with active structural works, including column casting, curing, retaining wall, and raft foundation progress

    June 2026

    Excavation, foundation laying, and concrete pouring are underway to cast structural columns.

    May 2026

    Reinforcement steel works were inspected by structural consultants BASE. Concreting of column footings for Tower D was successfully completed.

    April 2026

    DMC piling activities progressed steadily, while excavation and PCC laying works were undertaken for Tower D foundations.

    April 2026

    Shifting of old wooden planks and battens has been completed.Tower D footing and shuttering work is currently in progress

    March 2026

    Construction of the diaphragm wall was completed. Project machinery underwent inspection and received green-tag certification for operational readiness.

    March 2026

    Construction activities have started at the site. The dream has started to take shape.

    February 2026

    Site preparation and construction staging activities commenced, establishing the groundwork, logistics, and infrastructure required for project execution.